Project Overview
Redundant substation equipment decontamination and removal.
This project involved asbestos removal from all control buildings and decontamination of redundant PCB contaminated equipment from the Playford A & B Substations.
Once decontamination works were complete, a demolition crew from McMahon Services mobilised to remove all of the redundant equipment, including CB2 KV, CBs, CTs, CVTs, DNs, Bus, Bus Supports and Poles. Playford A also required removal of the transformer.
Works were undertaken in the following stages over a three month period:
- Stage 1 – Control Building Demolition
- Stage 2 – PCB Oil Removal / Substation Demolition
All works were completed utilising highly skilled and experienced in-house personnel from McMahon Services, including:
- Asbestos Removal
- PCB Removal
- Waste Transport
- Cranage
- Demolition
- Project Management